CONSTRUCTION TIMELINE



5 February 2019 Fence and Portaloo delivered

8 February 2019 - Land levelled / Cut and Fill

20 February 2019 - Piering & Formwork completed

21 February 2019 - Internal drainage installed and wafflepods delivered

22 February 2019 - Steel reinforcement and Wafflepods laid

25 February 2019 - Slab poured

5 March 2019 - External plumbing/drainage completed

12 March 2019 - Ground Floor frames

15 March 2019 - First Floor frames completed and windows installed

20 March 2019 - Enviroseal ProctorWrap installed

27 March 2019 - Internal Plumbing

15 April 2019 - Bricks delivered & Granitgard completed

2 May 2019 - Ground floor bricks completed & scaffolding put up

6 May 2019 - Roof Sarking

17 May 2019 - First floor bricks completed

23 May 2019 - Fascia, Gutter, Whirlybird Ventilator & Roof completed

30 May 2019 - Upper brick cleaned, eaves & cladding

7 June 2019 - Cladding completed & Render in Progress

21 June 2019 - Downpipes installed & Site clean

21 June 2019 -  Lower roof in progress, downpipes painted and scaffolding removed

21 June 2019 - Lower roof completed

4 July 2019 - Aircon rough ins

11 July 2019 - Electrical rough ins, cladding painted, rear and side scaffolding removed

18 July 2019 -  Gyprock

2 August 2019 - Staircase installed

9 August 2019 - Doors & Carpentry Fitout

19 August 2019 - Kitchen & Bathroom cabinetry installed , waterproofing completed

20 August 2019 - Painting started - walls and stairs

30 August 2019 - Benchtops and sinks installed

2 September 2019 - Render around garage and porch, shelves

4 September 2019 - Bathrooms & wet area tiling commenced 

9 September 2019 - Bathrooms & wet area tiling completed, main flooring installed, Electrical, Aircon and Plumbing fitoffs completed, Media Room surround sound cabling installed & shelving

16 September 2019 - Batten holders installed for pendant light provisions, ground floor downlights fitted, Gyprock patching, under stair storage enclosed