5 February 2019 - Fence and Portaloo delivered
8 February 2019 - Land levelled / Cut and Fill
20 February 2019 - Piering & Formwork completed
21 February 2019 - Internal drainage installed and wafflepods delivered
22 February 2019 - Steel reinforcement and Wafflepods laid
25 February 2019 - Slab poured
5 March 2019 - External plumbing/drainage completed
12 March 2019 - Ground Floor frames
15 March 2019 - First Floor frames completed and windows installed
20 March 2019 - Enviroseal ProctorWrap installed
27 March 2019 - Internal Plumbing
15 April 2019 - Bricks delivered & Granitgard completed
2 May 2019 - Ground floor bricks completed & scaffolding put up
6 May 2019 - Roof Sarking
17 May 2019 - First floor bricks completed
23 May 2019 - Fascia, Gutter, Whirlybird Ventilator & Roof completed
30 May 2019 - Upper brick cleaned, eaves & cladding
7 June 2019 - Cladding completed & Render in Progress
21 June 2019 - Downpipes installed & Site clean
21 June 2019 - Lower roof in progress, downpipes painted and scaffolding removed
21 June 2019 - Lower roof completed
4 July 2019 - Aircon rough ins
11 July 2019 - Electrical rough ins, cladding painted, rear and side scaffolding removed
18 July 2019 - Gyprock
2 August 2019 - Staircase installed
9 August 2019 - Doors & Carpentry Fitout
19 August 2019 - Kitchen & Bathroom cabinetry installed , waterproofing completed
20 August 2019 - Painting started - walls and stairs
30 August 2019 - Benchtops and sinks installed
2 September 2019 - Render around garage and porch, shelves
4 September 2019 - Bathrooms & wet area tiling commenced
9 September 2019 - Bathrooms & wet area tiling completed, main flooring installed, Electrical, Aircon and Plumbing fitoffs completed, Media Room surround sound cabling installed & shelving
16 September 2019 - Batten holders installed for pendant light provisions, ground floor downlights fitted, Gyprock patching, under stair storage enclosed
No comments:
Post a Comment