Thursday, August 9, 2018

ADMIN TIMELINE


2017 MILESTONES:

15 August - House on the market

19 August - 1st Open House

21 August - Offer received for sale of house

28 August - Offer accepted (house officially SOLD)

3 September - Holding Deposit paid to Wisdom Homes

14 October - Pre Tender meeting with Wisdom Homes

18 October - Exchanged on Land Contract, 10% deposit paid to Land Developer (Winten Developments)

15 November - Stamp Duty Paid

6 December - Draft Siting & House Plans received

16 December - 1st Variation to House Plans

17 December - 2nd Variation to House Plans

2018 MILESTONES:

4 January - 3rd Variation to House Plans

22 January - Tender Presentation at Wisdom Homes Head Office (Tender Acceptance Fee Paid)

25 January - Contract Accepted & remainder of deposit paid to Wisdom Homes

5 March  - Colours, Electrical & Landscaping Appointments at Head Office

6 March - Kitchen appointment at Timpelle Kitchens & Flooring appointment at Di Lorenzo Tiles

20 March - Accepted Di Lorenzo Quote (2 x changes in total)

22 March - Accepted Landscaping Quote (2 x changes in total)

5 April - Accepted Electricals Quote (4 x changes in total)

12 April - Accepted Sentinel Quote for Home Theatre Cabling

30 April - Accepted Timpelle Kitchens Quote (3 x changes in total - incurred Admin Change Fee)

15 May - Accepted Colours Quote (6 x changes/PCVs)

22 May - Accepted Ultra Air Quote

22 May - All Selections Finalised

25 July - Letter received from Solicitor advising to expect Land Registration in 3 to 6 weeks

25 July - Land Developer lodged plans to Council

1 August  - Land Loan Application started

9 August 2018 - Land Loan Approved

13 August 2018 - Land Registered

16 August 2018 - Construction Loan started

20 August 2018 - Construction Loan Pre-Approved

21 August 2018 - Contour Survey & Soil Test Completed

27 August 2018 - Land Settlement

27 August 2018 - Submission to Newpark Estate's Developer Review Panel for Approval

11 September 2018 - Developer Approval received

19 September 2018 - BASIX received

2 October 2018 - Council Submission Plans received

30 October 2018 - Amended Submission Plans received & reviewed

2 November 2018 - Submission Plans submitted to Council for Approval

15 November 2018 - Council Approved

28 December 2018 - Formal Application to Bank submitted (Land & Construction Loan)

2019 MILESTONES:

8 January 2019 - Amended Draft End Panel received and signed off

3 January 2019 - Bank requesting amendment to Progress Payments Schedule

10 January 2019 - Week long negotiations between Wisdom Homes / Broker / Bank regarding Progress Payments Schedule

15 January 2019 - Formal Approval received from bank

18 January 2019 - Signed Mortgage/Contract Documents

18 January 2019 - Final Construction Plans received

 21 January 2019 - Amended Final Construction Plans received and signed off

30 January 2019 - Remainder of deposit paid to Wisdom Homes

31 January 2019 - Production Estimating started (officially out of Admin!)

8 February 2019 - Loan Settlement Day

8 February 2019 - Land Loan refinanced