2017 MILESTONES:
15 August - House on the market
19 August - 1st Open House
21 August - Offer received for sale of house
28 August - Offer accepted (house officially SOLD)
3 September - Holding Deposit paid to Wisdom Homes
14 October - Pre Tender meeting with Wisdom Homes
18 October - Exchanged on Land Contract, 10% deposit paid to Land Developer (Winten Developments)
15 November - Stamp Duty Paid
6 December - Draft Siting & House Plans received
16 December - 1st Variation to House Plans
17 December - 2nd Variation to House Plans
2018 MILESTONES:
4 January - 3rd Variation to House Plans
22 January - Tender Presentation at Wisdom Homes Head Office (Tender Acceptance Fee Paid)
25 January - Contract Accepted & remainder of deposit paid to Wisdom Homes
5 March - Colours, Electrical & Landscaping Appointments at Head Office
6 March - Kitchen appointment at Timpelle Kitchens & Flooring appointment at Di Lorenzo Tiles
20 March - Accepted Di Lorenzo Quote (2 x changes in total)
22 March - Accepted Landscaping Quote (2 x changes in total)
5 April - Accepted Electricals Quote (4 x changes in total)
12 April - Accepted Sentinel Quote for Home Theatre Cabling
30 April - Accepted Timpelle Kitchens Quote (3 x changes in total - incurred Admin Change Fee)
15 May - Accepted Colours Quote (6 x changes/PCVs)
22 May - Accepted Ultra Air Quote
22 May - All Selections Finalised
25 July - Letter received from Solicitor advising to expect Land Registration in 3 to 6 weeks
25 July - Land Developer lodged plans to Council
1 August - Land Loan Application started
9 August 2018 - Land Loan Approved
13 August 2018 - Land Registered
16 August 2018 - Construction Loan started
20 August 2018 - Construction Loan Pre-Approved
21 August 2018 - Contour Survey & Soil Test Completed
27 August 2018 - Land Settlement
27 August 2018 - Submission to Newpark Estate's Developer Review Panel for Approval
11 September 2018 - Developer Approval received
19 September 2018 - BASIX received
2 October 2018 - Council Submission Plans received
30 October 2018 - Amended Submission Plans received & reviewed
2 November 2018 - Submission Plans submitted to Council for Approval
15 November 2018 - Council Approved
28 December 2018 - Formal Application to Bank submitted (Land & Construction Loan)
2019 MILESTONES:
8 January 2019 - Amended Draft End Panel received and signed off
3 January 2019 - Bank requesting amendment to Progress Payments Schedule
10 January 2019 - Week long negotiations between Wisdom Homes / Broker / Bank regarding Progress Payments Schedule
15 January 2019 - Formal Approval received from bank
18 January 2019 - Signed Mortgage/Contract Documents
18 January 2019 - Final Construction Plans received
21 January 2019 - Amended Final Construction Plans received and signed off
30 January 2019 - Remainder of deposit paid to Wisdom Homes
31 January 2019 - Production Estimating started (officially out of Admin!)
8 February 2019 - Loan Settlement Day
8 February 2019 - Land Loan refinanced