Wednesday, March 27, 2019
ENIVROSEAL PROCTORWRAP INSTALLED
The installation of this wrap was actually a BASIX requirement. Reading up on the advantages on Bradford's website (https://www.bradfordinsulation.com.au/home-insulation/wall-wraps/enviroseal-proctorwrap-wall-wrap), definitely worth the cost to do this!
Sunday, March 17, 2019
FIRST FLOOR FRAMES & WINDOWS INSTALLED
It's only been a few days since my last post and in just five days, our ground floor and first floor frames are up and windows have been installed. SS said in his weekly update call last Friday that next week's tasks will be internal plumbing, termite guard installation and also bricks will be delivered next week or the week after. Really happy with his communication so far! Hopefully the weather clears because our site is due for a cleanup, as per our SS. It has been extremely muddy onsite this week due to the heavy rains!
Wednesday, March 13, 2019
GROUND FLOOR FRAMES
Last week's weekly update call from our Site Supervisor indicated that our framework will get started on this week. Our neighbor one lot down messaged me via Instagram and gave us a heads up - our frames were up!